    <p style="font-weight:bold; display: inline; line-height:150%; font-size: 105%;">CITY OF COLUMBIA, MISSOURI
<br /> 
P.O. BOX 6015 COLUMBIA, MO 65205
</p></div>
  </div>
<div style="clear:both; text-align:center; padding-top: 20px;">
<h2 style="font-size: 200%;">FOR IMMEDIATE RELEASE</h2>
  <p style="font-size: 120%; margin-top: -5px; font-weight:bold;">October 3, 2017</p>
<p style="float:right; font-weight:bold; margin-bottom: 75px; font-size: 120%; text-align:right;">CONTACT: Columbia Public Works
<br />573-874-2489</p>

</div>
<div style="font-size: 110%; line-height:200%;"><h3 style="clear:both; margin-top: 75px;  margin-bottom: 10px; font-weight: bold; font-size: 170%;">Rollins Street, Brandon Road scheduled to open Oct. 7; Bingham Road access to close; project scheduled for completion in early November</h3>
<div class="content"><span style="padding-left: 50px;">(COLUMBIA, MO)</span> - <p style="display:inline;"><span style="font-weight: 400;">Columbia Public Works announced on Oct. 3 that the </span><span style="font-weight: 400;">Rollins Street and Brandon Road intersections are scheduled to open Saturday, Oct. 7, weather permitting. This week, workers are constructing a median island for the turn lanes and installing signs, weather permitting.</span></p>
<p><span style="font-weight: 400;">Once these intersections are completely open to traffic, the access to Bingham Road from Providence Road is scheduled to close for construction. Access to Bingham will be available via Brandon Road. </span></p>
<p><span style="font-weight: 400;">Bingham road is the last intersection of the Providence Road Improvement Project and is estimated to be completed by early November. The sidewalk along Burnam Road is also expected to be completed by early November.</span></p>
<p><span style="font-weight: 400;">Providence will continue to remain open during the work. Motorists, pedestrians and nonmotorized transportation users are urged to exercise extreme caution when passing through the work zone.</span></p>
<p><span style="font-weight: 400;">Project progress is available below as well as online at </span><a href="http://www.como.gov/publicworks/providence-improvement"><span style="font-weight: 400;">CoMo.gov/PublicWorks/Providence-improvement</span></a><span style="font-weight: 400;">.</span></p>
<br />
<p><strong>Project Phase Updates:</strong></p>
<ul>
<li style="font-weight: 400;"><strong>New Traffic Signals:</strong><span style="font-weight: 400;"> Installation of traffic signals along Providence Road at the intersection with Burnam Road and at the intersection with Turner Avenue.  </span><span style="font-weight: 400;"><br /></span><strong>Progress:</strong><span style="font-weight: 400;"> Signals went online Aug. 14.</span></li>
</ul>
<ul>
<li style="font-weight: 400;"><strong>Traffic Signal Removal:</strong><span style="font-weight: 400;"> Removal of the existing traffic signal along Providence Road at the intersection with Rollins Street.</span><span style="font-weight: 400;"><br /></span><strong>Progress:</strong><span style="font-weight: 400;">The signal was turned off and signal heads bagged on Aug. 14. Poles and bases were removed the week of Aug. 14. A right-turn lane has been constructed for northbound Providence onto Rollins as well as sidewalks and new pavement. The intersection is scheduled to open Oct. 7, weather permitting.</span></li>
</ul>
<ul>
<li style="font-weight: 400;"><strong>New Sidewalk:</strong><span style="font-weight: 400;"> Construction of a sidewalk along the south side of Burnam Road from Birch Road to Providence Road.  </span><span style="font-weight: 400;"><br /></span><strong>Progress: </strong><span style="font-weight: 400;">The sidewalk along Burnam Road is expected to be completed by the end of October, weather permitting.</span></li>
</ul>
<ul>
<li style="font-weight: 400;"><strong>Two Signalized Crosswalks: </strong><span style="font-weight: 400;">Enhancing the crosswalks at the signalized intersections at Turner and Burnam to meet or exceed current standards, including pedestrian signals.  </span><span style="font-weight: 400;"><br /></span><strong>Progress: </strong><span style="font-weight: 400;">These went into service Aug. 14.</span></li>
</ul>
<ul>
<li style="font-weight: 400;"><strong>Southbound right turn lane: </strong><span style="font-weight: 400;">Extension of the southbound right turn lane onto Stadium Boulevard from Providence Road.</span><span style="font-weight: 400;"><br /></span><strong>Progress: </strong><span style="font-weight: 400;">Expected to be completed the week of Oct. 9, weather permitting.  </span></li>
</ul>
<ul>
<li style="font-weight: 400;"><strong>Intersection access improvements: </strong><span style="font-weight: 400;">The intersections of Providence Road with Bingham Road and Kentucky Boulevard will be converted to right-in/right-out/left-in. The intersections of Providence Road with Rollins Street and Brandon Road will be converted to right-in/right-out.  </span><span style="font-weight: 400;"><br /></span><strong>Progress: </strong><span style="font-weight: 400;">Kentucky Boulevard is completed. Bingham is scheduled to close Oct. 7, once Brandon Road is open. The Brandon Road intersection is scheduled to open Oct. 7, weather permitting.</span><strong><br /></strong></li>
<li style="font-weight: 400;"><strong>Median Islands: </strong><span style="font-weight: 400;">Median islands to be constructed on Providence Road between Turner Avenue and Burnam.<br /></span><strong>Progress: </strong><span style="font-weight: 400;">Completed Sept. 11-13.</span></li>
</ul></div>
<br />
<div class="content"></div>
<br />
<div class="attachments"></div>
</div>
<div id="footerline">
<div style="margin-top: 75px; margin-bottom: 20px; text-align:center;"><p>City of  Columbia Vision<br>
  <em>Columbia is the best place  for everyone to live, work, learn and play.</em></p>
  <p>City of  Columbia Mission<br>
  <em>To serve the public through  democratic, transparent and efficient government.</em></p>
  </div>
  <p style="text-align:center;">-30-</p>
</div>
  <style>
   
  #pressrelease table, #pressrelease th, #pressrelease td{
border: 0px;
  }
#pressrelease{ margin:40px;}
  .attachments{margin-top: -10px;}
  </style><p>______________________________________________________</p>

<p>You have received this message because you subscribe to the City of Columbia's Web Mail service. To view linked material click on provided links or copy and paste them into your browser's address menu.</p>
<p>______________________________________________________</p>

<p>Archived press releases can be viewed online at:
http://www.como.gov/CMS/pressreleases/directory.php</p>