[Electrans-l] Tabulation of feedback will lead to preferred Option B transmission line routes
Southern Columbia Electric Transmission Line project
electrans-l at news.gocolumbiamo.com
Mon Feb 20 08:18:35 CST 2012
Transmission Line Project: February Update
Tabulation of feedback will lead to preferred Option B transmission
line routes
After holding an interested parties meeting last fall Columbia Water &
Light collected feedback for several months on the second route study
(Option B) for the proposed southwestern transmission line project. In
December the feedback was put into a database and submitted to the
engineering firm assisting with the project. An important part of
determining the preferred routes for Option B is to make sure the
selection matrix reflects the public opinion that was submitted. This
phase is almost complete and the results of the Option B analysis should
be finished within a month. A report will then be sent to the City
Council detailing the results of the selection matrix followed by
another interested parties meeting that will be scheduled for this
spring.
A time line for this project is available on the city’s web site:
www.gocolumbiamo.com/WaterandLight/Electric/ProposedElectricTransmission.php
-------------- next part --------------
An HTML attachment was scrubbed...
URL: http://news.gocolumbiamo.com/pipermail/electrans-l/attachments/20120220/41f77903/attachment.htm
More information about the electrans-l
mailing list