[Press Release] : FOR IMMEDIATE RELEASE: Milling planned for Orr Street, Stewart Road Aug. 12, overlay Aug. 15
Press Releases
pr-l at news.gocolumbiamo.com
Thu Aug 11 12:14:22 CDT 2016
FOR IMMEDIATE RELEASE
Contact: Barry Dalton
Public Information Officer
(573) 874-2489
Milling planned for Orr Street, Stewart Road Aug. 12, overlay Aug. 15
COLUMBIA, MO (August 11, 2016) - The Public Works Department announced on Thursday that Capital Paving, a subcontractor for the City of Columbia, plans to perform milling operations on Orr Street and Stewart Road Aug. 12 and then asphalt overlay the streets on Aug. 15, weather permitting. Orr Street will be improved from Park Avenue to Walnut Street. Stewart Road will be improved from Glenwood Avenue to Garth Avenue.
Motorists and nonmotorized transportation users should expect temporary lane closures while milling is being performed on Aug. 12. Flaggers will be on hand to allow through traffic. Traffic is permitted on the road once it is milled, no detours are necessary.
Contractor crews plan to return and perform an asphalt overlay on the same section of the road on Aug. 15, weather permitting. Motorists and nonmotorized transportation users should expect temporary lane closures while the work is being performed. Flaggers will be on hand to allow through traffic. Once the street is overlaid, traffic may drive on the asphalt almost immediately.
Motorists, pedestrians and nonmotorized transportation users should use caution in the work zones to protect themselves and the safety of workers.
Summary of Mill and Overlay Since April 2016
Spring 2016:
* Oak Cliff - Completed
* Shingo Court - Completed
* Gene - Completed
* Pineview - Completed
* Pine - Completed
* Yoko - Completed
* Rollins Road - Completed
Summer 2016:
* Texas (Creasy Springs to Garth) - Completed
* Remington (Creasy Springs to the "concrete section") - Completed
* Creasy Springs (Bear Creek bridge to Obermiller Road) - Completed
* Roundabout at Garth and Blue Ridge Road - Completed
* Providence Road (Blue Ridge to Smiley Lane)
* Pierre Street (Ballenger Lane to the west end) - Completed
* Mohawk Court (Mohawk Avenue to the end) - Completed
* Port Way (Bull Run to Canaveral) - Completed
* Appletree Court (Southhampton Drive to the end)- Completed
* Dustin Drive (Bethel to Cedar Ridge)- Completed
* Glencairn Court (Highland to the west end) - Completed
* Vawter School Road (Old Mill Creek to 1200 feet west)
* Lake Point Lane (Larail Drive to the west end)
* Larail Drive (Crestwood Lane to Burrwood Drive)
* Stewart Road (Glenwood to Garth) - Milling scheduled for Aug. 12, overlay Aug. 15
* Orr Street (Park to Walnut) - Milling rescheduled for Aug. 12, overlay Aug. 15
* Conley (Connector to 63 Bridge)
* Flora Drive (Olive Street to the end) - Completed
*Olive Street (Brown Station road to the end) - Completed
This release has the following attachments:
http://www.gocolumbiamo.com/CMS/pressreleases/downloadfile.php?id=1322
http://www.gocolumbiamo.com/CMS/pressreleases/downloadfile.php?id=1323
-30-
______________________________________________________
You have received this message because you subscribe to the City of Columbia's Web Mail service. To view linked material click on provided links or copy and paste them into your browser's address menu.
______________________________________________________
Archived press releases can be viewed online at:
http://www.como.gov/CMS/pressreleases/directory.php
______________________________________________________