[Press Release] : FOR IMMEDIATE RELEASE: [NEW SCHEDULE] New maintenance schedule announced for Rollins, Sinclair and Old Plank roads Aug. 1-5
Press Releases
pr-l at news.gocolumbiamo.com
Thu Jul 28 08:32:35 CDT 2016
FOR IMMEDIATE RELEASE
Contact: Barry Dalton
Public Information Officer
Public Works Department
City of Columbia, Missouri
(573) 874-2489
[NEW SCHEDULE] New maintenance schedule announced for Rollins, Sinclair and Old Plank roads Aug. 1-5
COLUMBIA, MO (July 28, 2016) - The Public Works Department announced a new schedule Thursday for ongoing work related to the spring mill and overlay of Rollins Road and the planned overlay of Sinclair Road and Old Plank Road.
The reinstalling of speed humps on Rollins Road, between Rothwell Drive and Westport Drive, that was originally scheduled for July 25-27 is estimated to be completed by August 1.
The overlay of Sinclair Road, between Stanley Pitts Lane and Route K, that was originally scheduled for July 28-29 is now planned for Aug. 2-5.
The overlay of Old Plank Road, between Route K and Campus Drive, that was originally scheduled for July 28-29 is now planned for Aug. 2-5.
This is a tentative work schedule subject to change due to weather or other factors. Motorists can expect minor delays and will be flagged through the work zone.
Previous Mill and/or Overlay Updates
7/19/16 - Summer mill and overlay road maintenance progress / update, July 25-29
7/11/16 - Mill and Overlay Street Maintenance Progress / Update [July 11] (Facebook/Twitter)
7/1/16 - Nighttime street maintenance on Broadway completed on schedule
6/24/16 - Nighttime street maintenance scheduled for Orr Street between June 27-30
6/17/16 - Nighttime street maintenance for East Broadway to begin June 27
6/2/16 - Summer Road Maintenance Progress / Update [June 2] (Facebook/Twitter)
5/31/16 - Summer Road Maintenance Progress / Update
5/24/16 - Road Maintenance Progress / Update
5/19/16 - Road Maintenance Progress / Update [May 20 - May 23]
5/12/16 - Street maintenance progress / update (May 12, 2016)
5/10/16 - Columbia street maintenance continues as planned
4/28/16 - Columbia Public Works - Roadwork April 19-29, 2016 [update]
4/27/16 - Columbia Public Works - Roadwork April 19-29, 2016 [update]
4/22/16 - Sidewalk Closures - Broadway at Fourth, Fifth, Sixth, Eighth, Ninth streets
4/18/16 - Columbia Public Works - Roadwork April 19-29, 2016
This release has the following attachments:
http://www.como.gov/CMS/pressreleases/downloadfile.php?id=1305
http://www.como.gov/CMS/pressreleases/downloadfile.php?id=1306
-30-
______________________________________________________
You have received this message because you subscribe to the City of Columbia's Web Mail service. To view linked material click on provided links or copy and paste them into your browser's address menu.
______________________________________________________
Archived press releases can be viewed online at:
http://www.como.gov/CMS/pressreleases/directory.php
______________________________________________________
If you would like to stop receiving messages, modify list options, or subscribe to other lists visit the Web Mail section of our Web site and follow the instructions provided.
http://www.como.gov/Web_Mail/
More information about the pr-l
mailing list