[planning-l] Proposed FY 2011-2014 CATSO Transportation Improvement Plan (TIP) Amendment
Planning and Development
pz-l at news.gocolumbiamo.com
Fri Mar 25 16:24:05 CDT 2011
Proposed FY 2011-2014 CATSO Transportation Improvement Plan (TIP) Amendment
County: Boone MoDOT Funding MPO Fiscal Year
Prior Prog.2011201220132014TOTALS
ProjectRoute 63 - Construction of new interchange with Route HENGState (AC) $866,000 $866,000
State$101,000$150,000$217,000 $468,000
MoDOT #5P0738Local
TIP #2011-16Other
Description:Construct new interchange and relocate southbound lanes from Ponderosa St. to Route H - 4.8 mile, a portion of the lane relocation is in CATSO Metro Area ROWFederal
State
Local
Other
Federal Source Agency CONFederal $0
Federal Funding Category State $2,881,000 $2,881,000
MoDOT Funding CategoryMajor Projects & Emerging NeedsLocal $0
Work or Fund CategoryENG/CONState (AC) $11,522,000 $11,522,000
Total Project Cost$15,737,000
AC Conversion Year - 2015; Anticipated Federal Category - NHS; State Funding-MoDOT TOTAL$101,000$150,000$15,486,000$0$0
$15,737,000
Description of Proposed Amendment
Attached is a proposed amendment to the CATSO FY 2011-2014 TIP. The request is for the addition of a project to reconstruct the US 63 & Route H intersection, including the relocation of approximately 4.8 miles of the southbound lanes of US 63. A portion of the lane relocation element of the project is within the CATSO planning area, although the intersection itself is not.
The tentative schedule is that this proposed MRP amendment will be considered for formal adoption at a public hearing at the May 26, 2011 Coordinating Committee meeting. If the requirements of project scheduling require it, a special meeting of the Committee may be scheduled.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://news.gocolumbiamo.com/pipermail/pz-l/attachments/20110325/24244f04/attachment.html>
More information about the pz-l
mailing list